Segment 1 Complete Work Package
Segment 1 is a widening project approximately 3.8 miles in length starting on the north end of Thomasville near AL-5. This segment ends approximately 1,500 feet north of Clayhill Drive. Segment 1 includes multiple drainage structures, mass excavation, grading, asphalt pavement, signage, guardrail, lighting and signals, and traffic markings.
Bids Due: November 20, 2025
Segment 6 Compete Work Package
Segment 6 is a widening project approximately 4.7 miles in length starting north of Scattered Oaks Drive, to approximately the intersection of AL-69 and SR-69. Segment 6 includes multiple drainage structures, mass excavation, grading, asphalt pavement, signage, guardrail, and traffic markings.
Bids Due: November 20, 2025